posted on: 8/2/2024

Weather permitting, a city contractor will pave Washington Street from Chestnut Street to Whittier Street starting Sunday, Aug. 4. The work is scheduled nightly from 8 p.m. to 6 a.m. through the week.

On-street parking will be prohibited from 7 p.m. to 7 a.m. during the project. Violators will be towed.

Motorists should expect road closures and detours. Flaggers will be on site to direct traffic. Local traffic and emergency vehicles will be allowed through the work zone.

The road will be milled full width and castings adjusted before paving. Drivers should be cautious of raised structures until paving is complete.

Washington Street paving begins Aug. 4

posted on: 8/2/2024

Weather permitting, a city contractor will pave Washington Street from Chestnut Street to Whittier Street starting Sunday, Aug. 4. The work is scheduled nightly from 8 p.m. to 6 a.m. through the week.

On-street parking will be prohibited from 7 p.m. to 7 a.m. during the project. Violators will be towed.

Motorists should expect road closures and detours. Flaggers will be on site to direct traffic. Local traffic and emergency vehicles will be allowed through the work zone.

The road will be milled full width and castings adjusted before paving. Drivers should be cautious of raised structures until paving is complete.

For more information, contact Community Services at 603-516-6450.